SIKA

Ai Process Design, Construct & Commission a New ATEX-Compliant Prepolymer Reactor Plant for Leading Construction Chemicals Manufacturer, Sika.

After
Before
Company logo

Client:

SIKA

Industry:

Building & construction chemicals

Project Site:

Leeds, UK

Objective:

Design, construct and commission a new ATEX-compliant prepolymer reactor plant.

Sika Ltd is a global leader in construction chemicals, specialising in high-performance products including sealants, adhesives, waterproofing systems, and specialty polymers used across infrastructure, commercial, and industrial construction markets. To support growing demand for advanced prepolymer-based formulations, Sika required a new dedicated reactor plant capable of safely handling flammable liquids while delivering consistent, repeatable product quality. The project required specialist expertise in hazardous area design, bulk chemical storage, and integrated process automation.

Ai Process was appointed as an EPCM contractor to deliver a fully turnkey solution—covering engineering design, procurement, construction, installation, and commissioning—while ensuring compliance with ATEX regulations and minimal disruption to ongoing site operations.

Construction Phase
Steelwork Installation

Ai Process Scope of Works

Ai Process delivered the project on a full turnkey EPCM basis, including:

  • Front End Engineering Design (FEED), detailed engineering, and process calculations
  • Design and construction of a new ATEX-rated prepolymer reactor plant
  • Bulk chemical storage and flammable liquid storage system design, including tank farm infrastructure
  • Supply, installation, and commissioning of reactor vessels, storage tanks, pumps, filters, and utilities
  • Full process control system design, PLC/SCADA, HMI integration, and recipe management
  • Hazardous area classification, ATEX compliance, and safety systems integration
  • Civil, structural steelwork, mechanical, electrical, and instrumentation installation
  • Testing, calibration, commissioning, and operator training
After
Before

Outcome and Benefits

Increased Production Capacity and Volume Expansion

The new 10,000-litre prepolymer reactor plant significantly increased Sika’s production capacity, enabling higher throughput and improved responsiveness to market demand. Enhanced bulk liquid storage, optimised material transfer systems, and automated batching removed previous bottlenecks, allowing the site to scale output efficiently while maintaining tight process control across all production campaigns.

Prepolymer Reactor

Full ATEX Compliance and Enhanced Process Safety

Ai Process designed the facility in accordance with ATEX hazardous area classification standards, HSG 176 guidance, and flammable liquid storage regulations. Integrated safety systems—including gas detection, pressure relief, SIL-rated instrumentation, and controlled hazardous area zoning—reduced operational risk, improved workforce safety, and ensured long-term regulatory compliance for handling volatile and flammable chemicals.

ATEX Rated Design

Improved Process Efficiency, Automation, and Product Consistency

Advanced process automation, recipe-driven control, and real-time data visibility improved batch accuracy, repeatability, and traceability. Automated dosing, vacuum systems, and controlled thermal media circuits reduced manual intervention, minimised process variability, and delivered consistent prepolymer quality—directly addressing common construction chemicals manufacturing challenges around yield, waste, and rework.

Reactor

Future-Proofed Infrastructure and Business Resilience

The plant was engineered with scalability and resilience in mind. Modular utilities, oversized services, and adaptable process control architecture allow for future capacity expansion, new product formulations, and additional tank farm services. This future-ready design strengthens business continuity, reduces capital project risk, and supports Sika’s long-term growth strategy in the construction chemicals sector.

ATEX Rated

Ai Process successfully delivered a fully integrated, ATEX-compliant prepolymer reactor plant for Sika Ltd in Leeds. The turnkey EPCM solution increased production capacity, improved safety and automation, and future-proofed critical manufacturing infrastructure. This project reinforces Ai Process’ position as a trusted chemical engineering consultancy and industrial plant construction partner for the construction chemicals industry.